LaPCS recently passed order - September 3rd, 2010
As per request, this is a synopsis of the recently passed order per the LaPCS in regards to the renewable portifolio standard. RPS
1. The Docket no. is R-28271. The history and findings can be accessed on the LPCS web site in the docket tab.
2. The order was officially filed on July 10,2010. It will go into effect after a 90 day review period which will allow for the development of the implementation process.
3. The driving force has been the issue that several States have developed RPS programs and the anticipation that there would be Fed. legislation in some regard.
4. The orginal attempt to develop such in La. begin in 3005 which resulted in the “Geaux Green” program.
5. With the change in the Fed. administration and passage of the Waxman/Markley legislation, the LPCS began the process again in May 2009 which entailed the establishment of a task force.
6. Following a series of meeting and inputs, the staff recommended that a “Pilot” program be established on June 15, 2010 which the LPCS adopted with unamious consent.
7. The goals are, “allow the Commission to accomplish its stated polilcy goals of: providing additioal resources that result in reliable and economical long-term electric supply; diversification of La. fuel mix; greater energy security through the use of indigenous resources; encouraging private investment; improving air quality; developing additional in-state renewable resources; ; andecouraging job creation andjob retention while avoiding the uncertanity associated with the cost impacts of a long term policy decision in an uncertain economic and political climate.”
8. As set out the “Pilot” program consist of two components, A. Research Component and B. RFP component.
1. Research component - These will be small scale research/evalation of renewable energy projects of either self-build and/or affilaited entities limited to no larger than 30MW for the entire component.
Affiliated entities may enter into 3 yr. contracts with utilities at standard cost plus $30 per MWH.
2. RFP component- each jurisdictional utility will be requried to conduct RFPs. The total capacity will be 350 MW based on an utility base load. Contracts will be for less than 20 years. Terms will be developed subject to PSC approval.
An exception will be an utility that is undertaking a bio-fuel co fireing. Terms and conditions are detailed.
Read the rest of this article »